Over the weekend we completed all scheduled network maintenance works on time during our customer’s planned June service shutdown in Tornio. However, there is still paperwork to be done and data feeding into our asset management systems.
Electricity was connected to the last transformer at 19:45 and Outokumpu could then continue its 24/7 manufacturing process of ferrite steel for its global customers.
We caused no changes to our client’s shutdown schedule, nor did we cause any additional disruption. All Aurora works were performed safely without any injuries.
Pentti Alatalo, Head of O&M, Tornio